Kitchen Renovation Frequently Asked Questions

A kitchen renovation typically takes between 4 and 12 weeks, depending on the size and complexity of the project.

Minor Kitchen Renovation (Approx. 4 Weeks)

A minor kitchen renovation usually takes about 4 weeks.
This includes:

  • New cabinets

  • New countertops

  • Tear-out and prep

  • Staying within the existing layout (no structural changes)

These projects are faster because plumbing, electrical, and walls remain in the same location.


Medium Kitchen Renovation (Approx. 6 Weeks)

A medium renovation typically takes around 6 weeks.
This may include:

  • New cabinets

  • Layout adjustments

  • Countertops

  • Electrical updates

  • Flooring

  • Painting

  • Full tear-out and preparation

Because trades are coordinated and finishes overlap, timing depends on scheduling and material availability.


Major Kitchen Renovation (10–12 Weeks)

A major renovation usually takes 10–12 weeks.
This includes:

  • Structural changes

  • Moving or removing walls

  • New doors or windows

  • Electrical updates

  • Flooring

  • Painting

  • Complete tear-out and rebuild

Structural work, inspections, and custom materials extend the timeline.


What can affect the timeline?

  • Permit approvals

  • Custom cabinetry lead times

  • Structural engineering requirements

  • Material availability

  • Unexpected issues behind walls


The best flooring material depends on your project, budget, and lifestyle.
For most residential renovations, we typically recommend:

  • Luxury Vinyl Tile (LVT)

  • Luxury Vinyl Plank (LVP)

  • Hardwood

  • Porcelain or Ceramic Tile


If You’re Starting Fresh

For busy families, LVT or LVP are often the best overall choice.

Why?

  • Very durable

  • Easy to maintain

  • Clean with a damp mop

  • More scratch-resistant than hardwood

  • Great for kitchens and main living areas

They offer the look of wood with lower maintenance and strong long-term performance.


Hardwood Flooring

Hardwood is a more elegant and natural option.

Pros:

  • Timeless appearance

  • Adds value to the home

  • Warm and classic look

Considerations:

  • Can scratch or dent more easily than vinyl

  • Requires more maintenance

Ideal for homeowners prioritizing aesthetics and resale value.


Porcelain or Ceramic Tile

Tile is typically used in wet or high-moisture areas, such as:

  • Kitchens

  • Bathrooms

  • Laundry rooms

  • Entryways

Pros:

  • Extremely durable

  • Water-resistant

  • Easy to clean

  • Can match floors and showers for a seamless design

Considerations:

  • Grout can be harder to keep clean

  • More labour-intensive to install


Matching Existing Floors

In renovation projects, we sometimes need to match or complement existing flooring. In those cases, we source products that blend well with what’s already in the home to create a cohesive look.


What About Carpet?

Carpet is still a great option for:

  • Stairs (especially runners)

  • Bedrooms

  • Areas where comfort and safety are priorities

It provides warmth, softness, and sound absorption.


Quick Summary

  • Best all-around choice for families: LVT or LVP

  • Most elegant look: Hardwood

  • Best for wet areas: Porcelain or ceramic tile

  • Most comfortable: Carpet in select areas

A kitchen renovation follows a structured process from contract signing to final installation. While timelines vary, most projects follow this order:


1. Contract Signing & Selections

Once the renovation agreement is signed:

All materials are selected and ordered, including:

  • Cabinets

  • Countertops

  • Sink and faucet

  • Flooring

  • Paint

  • Lighting

  • Backsplash

  • Cabinet hardware (handles)

  • Written specifications for new appliances

Cabinet lead times typically range from 4–8 weeks, depending on the manufacturer and customization.


2. Pre-Installation Preparation (1–2 Weeks Before Cabinets Arrive)

About 1–2 weeks before cabinet delivery, demolition begins.

This includes:

  • Removing old cabinets and countertops

  • Tear-out and disposal

  • Electrical or plumbing adjustments

  • Wall repairs and prep work

  • Ensuring the space is ready for installation

This preparation phase usually takes about one week, depending on scope.


3. Cabinet Installation (Approx. 1 Week)

Once cabinets arrive:

  • Cabinets are installed

  • Layout is finalized

  • Kitchen template measurements are taken for countertops

Cabinet installation typically takes about one week.


4. Countertop Templating & Installation (Approx. 2 Weeks Later)

After templating:

  • Countertops are fabricated

  • Installation is scheduled (usually about 2 weeks after templating)

During this stage:

  • Countertops are installed

  • Sink and faucet are installed

  • Backsplash installation follows


5. Final Touches & Completion

Once countertops and backsplash are complete:

  • Final plumbing connections are made

  • Appliances are installed

  • Finishing details are completed

Then it’s time to enjoy your new kitchen.


Typical Timeline Overview

From contract signing to completion, most kitchen renovations take:

  • Minor projects: 4–6 weeks

  • Medium projects: 6–8 weeks

  • Major renovations: 10–12+ weeks